During major repairs of steam turbine unit No4, 350MW from the state owned Agios Dimitrios Power Station, in North Greece, it was found that bearings were worn out and new white metal should be casted on. It took us 6 days to remove old white metal, apply new layer by casting and do the final machining. Final inspection in our quality control laboratory showed more than 97% bonding and 0 defects.